With the start of a new year, I want to provide an update on projects that will be pursued during the 1st quarter.
** Overlay of Berard Street — already approved by DOTD and work should begin by the middle of March.
** Veterans Park improvements — bid on work has been awarded. Work is scheduled to begin around February 1st.
** Carl Williams Park — design work is being finalized. Project should go out for bids by the middle of February.
** Refinery Street sidewalk project– design work is complete. Should be ready to be bid out project by the middle of February.
** Martin Street sidewalk project — finalizing funding through the MPO and DOTD so design work can be completed. Should get this approval by the end of February.
** North Bridge Subdivision pond drainage project — this project will be ready for bids by mid-February.
** Baldwin Street area drainage project — design work is complete and expecting to have final railroad company approval by mid-February. Anticipate going out for bids around March 1st.
** Sidonia Drive drainage project — design work is complete. Expecting to go out for bids by March 1st.
** Downtown sidewalk repairs and painting — anticipate completing the repairs by mid-February and all painting by mid-March.
** Reconfiguring of Berard Street/Mills Avenue intersection — anticipate DOTD beginning this work by mid-March.
** Widening of Dorsett Street at Berard Street — design work has been sent to DOTD. Anticipate beginning of work by the end of March.
** Reconstruction of Armentine Cove street — design work has been sent to DOTD. Anticipate beginning of work by the end of March.
More to come throughout the year…including major improvements to Parc Hardy!!
Mayor Ricky Calais